CONSTRUCTION UPDATE*

The work being done this week is repetitive for the next few weeks in each block being worked on. Simultaneous roadway reconstruction work along Miracle Mile from LeJeune Road to Salzedo and Ponce de Leon Boulevard to Douglas Avenue will continue this week along with paver work at Giralda Avenue.

MIRACLE MILE CONSTRUCTION –  February 20, 2017 to February 26, 2017

Block 300- Drainage excavation commenced on February 6, 2017. Drainage structure installation and pipe installation has started. The southernmost lane will remain closed (similar to other blocks).

Block 200 – Metal tree edging restraints to take place this week. Planter areas to be prepared for new landscaping. Preparation of sidewalk closest to the buildings will be prepared to receive pavers.

Block 100 –The bedding base is being prepared for the pavers and paver installation has started and will continue east of the crosswalk. Preparation of sidewalk closest to the buildings will be prepared to receive pavers.

Block 000 – Demolition and excavation for new drainage and electrical underground system, west of the mid-block crosswalk is in process. Trees have been installed on the west side of midblock crossing. One lane of traffic will remain open at all times on the south side of Miracle Mile from LeJeune Road to Douglas Road.

GIRALDA AVENUE CONSTRUCTION –  February 20, 2017 to February 26, 2017

The work being done this week is repetitive. Installation of pavers will continue east until completion. Bridalveil trees have been installed on the northeast corner the street. Underground electrical installation to start this week followed by paver installation at the Plaza. Temporary lighting has been installed. Drill shafts for the Catenary lighting will commence. We will continue to open paved areas from east to west as they are completed.

The street is closed to vehicular traffic; however, pedestrian access to the businesses will be maintained at all times for the duration of construction. Water barriers have been installed in order to separate the work zone  from  pedestrian  traffic.  Temporary  crossings  have  been  installed  and  will  be  relocated  as construction continues.

PARKING VOUCHERS

The City of Coral Gables has made parking vouchers for public parking garages available to merchants for the use of their customers. The vouchers were provided to the Business Improvement District (BID) for distribution to businesses being directly impacted by construction. Please call the BID at

305-569-0311 to pick up or ask for additional vouchers.

MIRACLE MILE VALET PARKING

The valet station on the 300 block is located by the Seasons 52 Restaurant on the north side of the block. All valet vehicles are being delivered to the alley behind Seasons 52 after 10 p.m.

GIRALDA AVENUE VALET PARKING VOUCHERS

In addition to the parking vouchers provided to merchants for nearby garages, Giralda’s Restaurant Row is also offering free valet. In partnership with the City, Restaurant Row merchants on the 100 block of Giralda Avenue will provide complimentary valet vouchers to their customers, at their discretion. Merchants requiring additional vouchers should contact the Parking Department at 305-460-5541.

A valet station is now operating at the northeast corner of Ponce de Leon Boulevard and Giralda Avenue for lunch (11a.m. – 5 p.m.) and dinner (6 p.m. – 12 a.m.) Monday to Saturday. There is another station on the west side of Galiano Street between Giralda Avenue and Aragon Avenue operating for lunch (11a.m. – 4 p.m.) and dinner (6 – 11 p.m.) Monday to Saturday. The valet station will remain open until midnight on Friday and Saturday.

NEW WATER MAIN ALONG MIRACLE MILE FROM SW 37 TO 42 AVENUES

Project Information / Schedule

The Miami-Dade Water and Sewer Department (WASD) has embarked on a capital improvement project that will make necessary upgrades to the water and sewer infrastructure. WASD is installing a new 16-inch Water Main along Miracle Mile (on the north side of the median), from SW 37 to 42 Avenues.

Phase 2 of the project is currently underway (started Tuesday, January

17th with a projected completion date of May 2017). The construction work will occur between 10:00 p.m. and 10:00 a.m., Sunday to Thursday only. The work will require phased roadway closures of both lanes on the north side of Miracle Mile during the construction times at night.  Lanes will reopen to traffic by 10:00 a.m. every morning.  The site will be cleared of construction equipment as the street reopens each  morning.  Block-by-block  construction  work  will  begin  on  LeJeune  Road,  progressing  toward Douglas Road. On-street parking will be impacted by this project between the hours of 10:00 p.m. and

10:00 a.m. For a list of municipal parking garage and valet parking locations, visit www.gablesstreetscape.com.  When the street is closed at 10:00 p.m. restaurant customers on the closed block will be provided an alternative location for retrieving their vehicles.

For More WASD Information:

Luis Rojas                                                             Adriana Lamar

Construction Manager                                          Chief of Public and Governmental Affairs

Tel: 786-402-1292                                                Tel: 786-552-8087

E-Mail:  [email protected]     E-Mail:  [email protected]

HAPPENINGS AROUND TOWN

JAZZ IN THE GABLES Every Tuesday from 6 – 7:30p.m. The Plaza at 150 Miracle Mile Courtesy of the McBride Family

The City of Coral Gables invites you to enjoy a jazz concert featuring Javier Nero Jazz Orchestra on Tuesday evening in a beautiful outdoor setting.

*Merchants wanting to participate should call 305-460-5392 or email [email protected]

WELLNESS WEDNESDAYS Yoga this week!

Every Wednesday from 6 -7p.m. Through May 2017

The City of Coral Gables is offering free yoga, boot camp and zumba classes in partnership with green monkey!

Join us every Wednesday at The Plaza at 150   Miracle   Mile,   courtesy   of   the McBride Family, from 6 – 7p.m. Classes will be held on weather-permitting basis. For    a    schedule,    visit    the    website coralgbables.com/wellnesswednesdays.

HARD HAT HAPPY HOUR

Every Wednesday starting at 5p.m.

Grab a bite, get a drink, and talk some shop. It’s all happening Wednesdays in Downtown  Coral  Gables.  Join  the Business Improvement District (BID) every Wednesday for Hard Hat Happy Hour and enjoy the best midweek pick- me-up Miami has to offer. Visit all participating restaurants and bars. Cheers!

*Merchants wanting to participate should call the BID at 305-569-0311. For more information, visit www.ShopCoralGables.com.

STAY IN TOUCH

Please remember to visit the Gables Streetscape website for the latest up-to-date information on construction and programming, www.gablesstreetscape.com. Have questions or concerns? Please call the Construction Information Hotline at 786-444-6383 or contact Beatriz Echemendia, Public Information Officer at 786-437-6171 / [email protected] or Roberto Gutierrez at 786- 437-6786 / [email protected]

*The  construction  schedule  is  subject  to  change  due  to  unforeseen  circumstances  and/or  weather conditions. Access to businesses will be maintained at all times.

CALENDAR OF EVENTS

<< Aug 2017 >>
MTWTFSS
31 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3
Click on month name to see the full month's calendar.